On Slow Track: Metro project to take over 3 years for completion
   Date :28-Mar-2024

On Slow Track 
 
 
 
 
 
Staff Reporter
 
 
Although Metro officials are working tirelessly to ensure that Metro train becomes available to people at the earliest but it would take time to construct the first route of AIIMS to Karond area. Experts said that commercial run of Metro will begin from July or August but only in parts of the city. Entire Metro project would take time to get complete. The construction plan of route from AIIMS to Karond includes twin tunnel and two under ground stations which is yet to be started. However, selected agent has got the contract letter this week and it would take at atleast two months to start the work. Officials said that to prepare the two under grounds and tunnels it would take around three years.
 
In first phase, AIIMS to Karond route is 16.8 km long and its 13.4 km of area will be elevated. Remaining 3.4 km of area will be there on land. Construction plan includes 12 elevated and two under ground stations. Officials informed that independent safety audit and valuation of metro project will be held by a private company for both Bhopal and Indore city. Independent Safety Assessor will be testing the co-ordination and technical run of Metro train at least for three-and-half years. Assessment will be beginning from Subhash Nagar depot in Bhopal. Last year Madhya Pradesh Metro Rail Corporation had called offer to appoint a consultant for the same. Construction of Metro was began in Bhopal from Subhash Nagar to AIIMS during year 2018. Continuing the work of Subhash Nagar to AIIMS, working on other routes including Karond was began. Officials said it would take around 769 crores on construction of land areas and twin tunnels. According to metro corporation officials, Bhopal and Indore city has received five sets each of Metro trains.
 
One train is already there on track for final trial and three trains are being run in depot for testing. After, Model Code of Conduct imposed, commercial run of metro has been postponed for July or August. One of the five trains has completed its trial while three are ready to run for the final trial. All the trains are undergoing through technical testing. According to officials a total of 27 trains will be coming to Bhopal and 25 trains to be sent to Indore city. Each train has three coaches. Technicians said that it is mandatory to run the new coaches at least for 2,000 km for the final trial. A team of 50 engineers, supervisors and staff are deployed to bring the two trains on main track.