Underconstruction flyover from Chichbhavan on Wardha Road.
Staff Reporter :
- The work began on October 3, 2025, and the scheduled completion date is October 2, 2027
- 27 per cent work of the project completed
The Rs 619 crore six-lane flyover connecting Chichbhavan to MIHAN Interchange is gathering pace, with 27.48 per cent of the project completed by November 17. However, construction barricades, narrowed carriageways and rampant wrong-side driving are turning the stretch into a daily traffic bottleneck, leaving commuters travelling towards Butibori facing journeys of nearly 45 minutes instead of the usual 20 minutes.
The 2.69 km elevated corridor is a crucial infrastructure project on National Highway-44, serving as a major gateway connecting Nagpur with Butibori, Wardha, Hyderabad, Yavatmal and Mumbai.
The project also includes widening of an additional 3.05 km stretch of the existing four-lane highway into a six-lane road with paved shoulders, taking the total project length to 5.74 km.
The National Highway Division of the Public Works Department (PWD) is executing the project under the Hybrid Annuity Mode (HAM). The work began on October 3, 2025, and the scheduled completion date is October 2, 2027.
According to the department’s latest progress report, 37 of the 63 planned foundations have been completed, along with 34 pier caps, while work on three more is underway.
Of the 784 precast segments required for the flyover, 264 have been cast. Segment erection has also begun, with 12 of the 62 spans completed.
The project has an awarded contract value of Rs 332.01 crore, which is 24.30 per cent below the estimated project cost. Financial progress of Rs 90.684 crore has been recorded so far.
While construction is progressing, traffic management on the ground remains a major concern. Barricades have reduced the available road width, while removal of existing dividers and merging of service roads with the main highway have created confusion among motorists.
Several local motorists, including those travelling to shops, schools and workplaces, are using the combined carriageways in both directions to avoid longer U-turns.
This wrong-side driving, coupled with roadside parking and commercial activity, has increased the risk of accidents and slowed traffic considerably.
Once completed, the flyover is expected to allow through traffic to bypass local junctions and improve connectivity to MIHAN and adjoining areas. The project also includes service roads, RCC drains, culverts, a toll plaza, 12 bus bays, two major intersections and 24 minor intersections.