MP Transco develops country’s first network islanding scheme in Jabalpur
   Date :26-Nov-2026

MP Transco develops countrys first network islanding scheme in Jabalpur
 
By Ashish Rajput
 
Jabalpur, 
 
Jabalpur Islanding Scheme is designed to automatically isolate a designated section of Jabalpur electricity network from the main grid under emergency conditions. Once separated, this network will function as an independent electrical island, drawing power from Amarkantak Thermal Power Station  
 
In a major initiative to strengthen power security, Madhya Pradesh Power Transmission Company Limited (MP Transco) has developed the country’s first-ever transmission network islanding scheme in Jabalpur. The system is designed to ensure continuity of electricity supply to critical installations and essential services even during major disturbances in the national power grid. The innovative scheme will provide an additional layer of protection to strategically important defence establishments, hospitals and emergency services in Jabalpur, ensuring that large-scale grid failures do not disrupt their essential operations.
 
The Jabalpur Islanding Scheme is designed to automatically isolate a designated section of the city’s electricity network from the main grid under specified emergency conditions. Once separated, this section will operate as an independent electrical island, drawing power from the Amarkantak Thermal Power Station. This arrangement will help maintain electricity supply to identified critical installations even when the larger grid experiences severe disturbances. 
 
Advanced technology for reliable power supply
 
The scheme incorporates an advanced Phasor Measurement Unit (PMU)-based monitoring and control system to continuously assess grid conditions and maintain a balance between electricity generation and demand within the isolated network. Automated switching arrangements and protection relays will facilitate rapid separation from the main grid whenever required, helping prevent cascading failures and widespread power outages. The use of PMU technology will also enable faster response and provide better real-time visibility to the State Load Dispatch Centre (SLDC) and Western Regional Load Dispatch Centre (WRLDC) during the isolation and restoration processes. The project is being implemented with financial assistance from the Central Government. Under the funding arrangement, 90% of the project cost will be borne by the Centre, while the remaining 10% will be contributed by the State Government and concerned local agencies. 
 
CEA recommends Jabalpur Islanding Model to other states
 
State Load Dispatch Centre (SLDC) Jabalpur Chief Engineer Rajesh Gupta told ‘The Hitavada’ that the Jabalpur Islanding Scheme, developed using state-of-the-art technology, is unique in the country. Recognising its significance, the Central Electricity Authority (CEA) has approved the Jabalpur Islanding Scheme as a model project and advised other states to consider adopting the same model to protect essential services from major power grid disturbances.Gupta further informed that the project is in the final stage of implementation and is likely to be commissioned by the end of January 2027.