Kamptee-Kanhan 1.3 km metro DPRsubmitted; extension cost at Rs 300 cr
   Date :12-Feb-2026

Kamptee-Kanhan  km metro
 
 
By Simran Shrivastava :
 
MAHARASHTRA Metro Rail Corporation Limited (MMRCL) has finallysubmitted theDetailed ProjectReport (DPR) for extending thePhase-IImetro alignment in theNortherncorridor (Orange Line) from Kamptee upto Kanhan river.Theextension,estimated at around Rs 300 crore, has completed internal clearances within the organisation and now awaits final approval from State and Union Government. This marks a decisive planning milestone for the proposed 1.3 km addition, said a Metro official. Officials said, Metro got a demand for taking up the extension because residents of Kanhan region do daily updown from Butibori and otherplaces.Further,manyof the people from Kanhan are dependent on Nagpur city markets. Hence, decision to extend the link upto Kanhan was decided. The proposed stretch is engineered to include a 500-metre steel viaduct across the Kanhan River.
 
The addition has raised the operational footprint of Phase-II to beyond 45 km and increased the number of stations on the Kamptee route from 12 to 13, integrating Kanhan into the metrogridplanned for theregion. The DPR positions the extension asa strategic mobility intervention for settlements and industrial activity beyond Kanhan,strengthening last-mile connectivity in the Northern periphery,while preserving continuity with the approved PhaseII framework.
 
By documenting alignment geometry, structural typology, cost architecture, and integration logistics, the report places before decision-makers the full technical and planning rationalerequiredat theapproval stage. The extension is intended toservethousandsofresidents in the Kanhan area and surrounding industrial pockets by linking themdirectly to themetro spine envisioned under PhaseII.
 
The proposal under scores that the river crossing, station augmentation, and alignment continuity have been resolved at the planning level, enabling authorities to evaluate the projecton fully articulated technical and financial parameters. The submission comes amid the broader national emphasis oncapital expenditure and infrastructure-led growth, where urban mobility projects continue to form a central pillar of public investment strategy. The Kamptee-Kanhan addition will represent a calibrated expansion of themetro network, extending its reach deeper into the northern growth corridor while maintaining structural and operational harmony with the existing Phase-II design. “Now after State Government studies the DPR, it will forward the proposal to Ministry of Housing and Urban Affairs (MOHUA) for latter’s clearance, after this it will come back to metro,” the official noted. On why Metro made a different DPR than theone forPhase-II, the official said that because the demand came much later, they had to do this separately.