Staff Reporter :
THE National Green Tribunal
(NGT), Central Zonal Bench,
Bhopal, on Tuesday directed the
Water Resources Department
(WRD) to address the alleged
continuous outflow of water from
Kerwa Reservoir within 15 days.
The direction followed the halting of a ground-truthing exercise
on September 9 over objections
that Kerwa had not reached its
Full Tank Level (FTL).
Applicant raises water outflow issue: The issue was raised
by NGT applicant and survey
committee member Dr Subhash
C Pandey. The Tribunal had on
August 31 directed identification, demarcation and groundlevel verification of encroachments and maximum water levels at Kerwa, Bhoj Wetland and
Kaliyasot reservoirs. The next
hearing is scheduled for
September 30. Committee seeks
tribunal guidance:
Representatives of the MoEFCC,
CPCB, MPPCB, WRD, Madhya
Pradesh State Wetland Authority,
MANIT, the applicant and environmental experts were present
during the September 9 survey.
According to the submission,
some officials sought stoppage
of the exercise citing non-attainment of FTL, while several members favoured continuing the verification.
Alleged bypass causes water
loss: Pandey alleged that substantial water was continuously
flowing through an artificial canal
or bypass. He questioned how the
reservoir could attain or retain
FTL while the bypass remained
open and suggested measures
such as stone pitching or a temporary stop-dam.
He also alleged
that over 90% of boundary pillars installed in 2023 had disappeared. Independent probe
sought: Pandey has sought
resumption of the groundtruthing exercise, stoppage of
the alleged bypass outflow and
an independent inquiry by the
MoEFCC and/or CPCB. He also
sought KML files of the three
water bodies to verify earlier
demarcations. The allegations
have not been independently
established. Survey covers multiple areas:The special team also
conducted ground verification
at several locations around Bhoj
Wetland and Kaliyasot, including Khanugaon, the under-construction cruise site, Army Sports
Area, Kohefiza, Halalpura,
Bhouri, Kolukhedi, Khajuri Sadak
and Bairagarh. Officials and
experts recorded water boundaries and surrounding conditions during the exercise.
Construction found near
Kaliyasot: At several locations,
water was found extending
around five to 10 feet beyond
boundary pillars, while water
was also seen flowing over retaining walls. The survey team reported that a road had been constructed through the waterlogged
area of Kaliyasot, with large
restaurants and commercial
structures allegedly located within or close to the reservoir boundary. Bada Talab hearing today:
The NGT is scheduled to hear the
Bhoj Wetland, including the
Upper Lake or Bada Talab, matter on Wednesday.
The remaining submissions
and drone survey report covering the Bhoj Wetland and
Kaliyasot are also expected to be
placed before the Tribunal.