Staff Reporter :
MOBILEtowers in the State capital will no longer be cleared
merely on availability of land.
The National Green Tribunal
(NGT), Central Zonal Bench, has
directed the Urban Development
Department and Bhopal
Municipal Corporation (BMC)
to frame a Standard Operating
Procedure (SOP) for installation
and operation of telecom towers within city limits.
Under the proposed framework, locations in and around
schools, hospitals, hostels, playgrounds, jails and densely populated areas will be governed by
local land-use and building construction rules. The SOP must
incorporate land-use status,
building bylaws, environmental
norms and radiation compliance
before permission is granted.
Citing expert reports and available scientific literature, the
Tribunal observed that there is
at present no conclusive evidence of identifiable harm from
non-ionising radiation emitted
by telecom networks, in line with
WHO assessments. However, it
stressed the need for a clear local
regulatory mechanism.
Radiation certification mandatory: Every tower must be
checked by the Department of
Telecommunications’ Telecom
Enforcement Resource and
Monitoring (TERM) Cell.
Telecom providers will have to
submit a self-certificate within
15 days of testing, proving emissions are within prescribed DoT
limits. Operations can begin only
after this. Regular audits have
been ordered, with immediate
corrective action if limits are
breached. DG sets under pollution ambit: Diesel Generator sets
powering towers will now require
prior consent from the State
Pollution Control Board, with
adherence to air and noise emission standards.
Special focus on vulnerable
areas: The NGT order reiterates
its earlier precautionary principle direction, BMC was previously asked to survey towers
within 100 metres of schools and
hospitals, to ensure safety norms
are not compromised.
The new SOP is expected to be
finalised soon, bringing uniformity and transparency to tower
approvals in Bhopal.