Staff Reporter :
IN A major milestone for emergency operational readiness, the
Madhya Pradesh Power
Generating Company Limited
(MPPGCL) successfully carried
out its first-ever ‘Black Start Mock
Drill’ on Thursday. The vital joint
exercise tested the power system’s capability to systematically restore electricity generation
in the event of a total or partial
grid blackout.
Conducted between 11:30 am
and 1:51 pm, the drill brought
together technical teams from
Satpura Thermal Power Station
in Sarni, Indira Sagar
Hydroelectric Project in Khandwa
and State Load Dispatch Centre
(SLDC). The operation adhered
strictly to the provisions outlined
in the Indian Electricity Grid Code
(IEGC), 2023.
A ‘Black Start’ is a critical gridrestoration procedure where a
generating plant uses self-starting energy sources to bring auxiliary systems online without
relying on external power.
During
this drill, electricity was routed
from Indira Sagar Hydroelectric
Project via a specialised islanding mechanism to jumpstart the
500 MW (2×250 MW) Satpura
Thermal Power Station.
Engineers successfully charged
400 kV system, energised
the station transformer and
restored essential auxiliary power systems in a precise, predetermined sequence.
All key electrical parameters
were continuously monitored
and successfully met within the
stipulated technical guidelines.
Chief Engineer and Station Head
S K Lilhore, along with
Superintending Engineer
Yashwant Varathe and other
senior technical staff, oversaw
the operation.
The successful trial highlights
MPPGCL’s technical expertise
and inter-agency co-ordination.
By validating its disaster
response protocols, the utility
company has proven its ability
to swiftly handle major grid
emergencies, ensuring minimal
downtime and rapid power
restoration for the State.