NEW DELHI :
WITH the bullet train project making rapid progress, a photo of the Mumbai-Ahmedabad High Speed Rail (MAHSR) has been put up in the Railway Ministry. The picture has been posted near Gate Number 4 of the Ministry.
The (MAHSR) Project (508 km) is under execution with technical and financial assistance from the Government of Japan.
The Project will pass through the states of Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati. The
Railway Ministry has expressed confidence of running the country’s first bullet train between Surat and Bilimora this year.
Out of the total 12 stations, foundation works have been completed at 8 stations (Vapi, Bilimora, Surat, Bharuch, Anand, Vadodara, Ahmedabad, and Sabarmati). Seventeen river bridges have been completed. Work is in advance stage for 4 major river bridges (Narmada, Mahi, Tapti and Sabarmati) in Gujarat & in progress in 4 river bridges in Maharashtra. Work on Depots (Thane, Surat and Sabarmati) is in full swing.
Civil works at Bandra Kurla Complex (BKC) are progressing satisfactorily. Excavation works have achieved about 91% progress, and concreting works are at various stages, with 100% completion of the basement slab at Level-4.